Decoding the OEE Calculation: Translating OEE Metrics into Tangible Losses

The following OEE funnel is a great way to visualize how losses in availability, performance, and quality impact OEE and your throughput.

OEE
Availability
Performance
Quality Manufacturing Metrics
Décoder le calcul de l'OEE : Traduire les mesures de l'OEE en pertes tangibles

Overall Equipment Effectiveness (OEE) is a universal metric for assessing manufacturing operational efficiency. While there's lots of information out there on how to calculate OEE and what it is, in this article we highlight how Worximity measures your OEE in its production monitoring solution.

OEE and Its Factors: Identifying Loss Areas

The OEE score serves as a snapshot of your operational status, with its three key factors—Availability, Performance, and Quality—playing pivotal roles in pinpointing areas where losses occur and guiding improvement efforts.

Let’s start by imagining a manufacturing plant with a production line that has:

  • an 8-hour shift working 5 days a week (40 hours/week) and,
  • a target rate of 20 units/hour (800 units/week).

Availability Loss: Unplanned Downtime

When a machine isn't running as it should be due to unplanned downtime like machine breaks or material shortages, it results in a loss of availability and reduced production time. It's important to note that scheduled downtime, such as breaks and lunches, is excluded from OEE calculations and falls under Overall operations effectiveness (OOE).

In the scenario above, if a total of 7.5 hours of planned downtime is scheduled for the week and the production line loses another 12.5 hours in unplanned downtime, it will produce 400 units instead of the potential 650 resulting in an availability of 62%.

Performance Loss: Speed Inefficiencies

Performance loss occurs when a machine operates below its maximum speed.

Returning to our example, if the line runs at 16 units per hour instead of 20 units per hour, it will produce 320 units out of the expected 400 – a performance of 80%.

Quality Loss: Falling Short of Standards

Quality loss happens when produced units don't meet required standards, resulting in rejects and the need for rework. In our scenario, 35 units were rejected during the quality check process generating a quality score of 89%.

Summary: Quantifying Losses in Time, Units, and Money

When any of the OEE factors falls below 100%, it indicates a quantifiable loss in terms of time, units, and money. In the given example, the net units left were 285 out of the planned 650, highlighting the impact of unplanned downtimes, suboptimal speed, and quality issues.

The OEE funnel

By diligently monitoring and optimizing these factors, you can make significant improvements at every stage of your production process, leading to increased efficiency and cost savings.

OEE Benchmarks Setting Realistic Targets

Seiichi Nakajima introduced the concepts of OEE and total productive maintenance (TPM) in the 1970s. In his book, Introduction to TPM, he suggested four “world-class” numbers: availability of 90%, efficiency of 95%, and quality of 99%, yielding an OEE of 85%.

  • 100% OEE is considered perfect production
  • 85% OEE reflects world-class operations
  • 60% OEE is typical and average
  • 40% OEE is low but not uncommon

Industry-specific variations exist, and targets may differ based on company size, type, and operational nuances.

In assessing your OEE, it's crucial to consider the realistic dynamics of your operations. Differences exist between manufacturers with large and small product mixes, influencing target numbers for availability, efficiency, and quality. Start by downloading our free OEE calculator.

Want to learn more?
Download the ebook
Related blog articles

Articles connexes

Retour au blog
Nous vous remercions ! Votre demande a bien été reçue !
Oups ! Un problème s'est produit lors de l'envoi du formulaire.
9
Mars 2020

OEE Data Collection Software Made Simple

English
12
Fév 2020

Measuring OEE with MULTIVAC Packaging Equipment

English
8
Fév 2021

How to Calculate OEE with Worximity Technology

English

Articles connexes

Retour au blog
Nous vous remercions ! Votre demande a bien été reçue !
Oups ! Un problème s'est produit lors de l'envoi du formulaire.
22
mai 2019

Quel type de leader 4.0 êtes-vous?

Croyez-vous que vous avez ce qu'il faut pour réellement servir de leader 4.0? Apprenez-en plus sur les différents types de leaders et leurs caractéristiques.

French
11
Déc 2019

Pénurie de main d'oeuvre dans le secteur manufacturier - Prévisions pour 2020-2028

Selon plusieurs enquêtes, le secteur manufacturier pourrait faire face à de sérieuses pénuries de main-d'œuvre. Voici comment y remédier.

French
4
Mars 2022

Manufacturing Leadership: How to Create Ownership Across Your Work Teams

Find out how fostering ownership across teams is essential to being an effective manufacturing leader.

English